Large new bridge connecting I-24 to S. Church St. in Barfield area continues to see progress

  Email   Print
Standing midway up bridge looking towards I-24
Looking thorough the rebar that will soon be used to reinforce concrete retaining walls.
Standing on the I-24 side of the bridge looking towards S. Church St. The rebar has just been completed and concrete will soon be poured.
Under the bridge looking up. In the background is the CSX rail line that goes between Murfreesboro and Shelbyville. Before the tracks is the Middle Fork Stones River.
This shot is looking towards I-24.

The City of Murfreesboro continues to see progress on a massive new bridge connecting Joe B. Jackson Parkway to County Farm Road, which is now Veterans Parkway. City Manager Rob Lyons told WGNS in a past interview...

 

Prior to the start of the project, Murfreesboro Engineer Chris Griffith confirmed the bridge is indeed the largest bridge the city has ever undertaken.

See pictures that were taken last Sept. of 2013 to compare the progress to the above photos: More pictures  click here...

 

Related Articles
Read more from:
News
Tags: 
bridge, County Farm Rd., Murfreesboro, Murfreesboro news, S. Church St., Veterans Parkway, WGNS
    
  Email   Print

Powered by Bondware
News Publishing Software