Count Your Blessings, Don't Watch The Mercury!

Nov 19, 2022 at 07:30 am by WGNS


(MURFREESBORO) I know that winter will not officially arrive until December 21, 2022, but temember--this is THANKSGIVING week and motorists might be better off counting their blessings rather than watching the mercury. Murfreesboro Transportation's Deputy Director Ram Balachandran warned of construction areas that might challenge local drivers between today and November 26, 2022.

City Construction Projects 

Oakland Court Development (Lokey Ave and Academy St)

ADVERTISEMENT

Expected Road Closures:  Monday through Friday:  Site construction work continues.  Academy St is closed to through traffic between Palm Ct and Hembree St.  Lokey Ave is also be closed at Academy St.  Appropriate traffic controls and detours will be in place.

Brinkley Rd Improvement Project (between Blaze Dr and Timber Creek Dr)

Expected Lane Closures:  Monday through Friday:  Roadway construction work continues on Brinkley Rd.  There will be intermittent lane closures and traffic interruptions.  Also, bridge work continues Brinkley Rd just to the south of Timber Creek Dr.  Timber Creek Dr is closed to through traffic at Brinkley Rd.  Traffic is detoured onto Willowbend Dr.  Appropriate traffic controls and detours will be in place.  

Medical Center Pkwy Turn Lane and Signal Improvement (between Honeylocust Ln and Willowoak Trl)

Expected Lane Closures:  Monday through Friday, 8:30 am to 3:30 pm:  As part of private development, storm drain, right turn lanes and traffic signal improvements will be made along the north side of Medical Center Pkwy between Honeylocust Ln and Willowoak Trl.  Westbound traffic on Medical Center Pkwy will be reduced to one lane.  Eastbound traffic will not be affected.  Appropriate traffic controls will be in place.

Turn Lane & Water Line Installation Work (Yeargan Rd between Misflower Ln and Clarawood Way )

Expected Lane Closures:  Monday through Friday, 8:00 am to 4:00 pm:  Construction crews will be making turn lane improvements along Yeargan Rd between Misflower Ln and Clarawood Way.  Traffic on Yeargan Rd will be reduced to one-lane flagging operation.  Appropriate traffic controls will be in place. 

Atmos Energy Gas Line Installation Work (Bell St just west of the Bridge)

Expected Lane Closures:   Monday through Friday, 9:00 am to 3:00 pm:  Atmos Energy crews will be performing gas line work along Bell St.  Bell St will be reduced to one-lane flagging operation.  Appropriate traffic controls will be in place.

Mill and Overlay Work (Sulphur Springs Rd at Irongate Blvd)

Expected Lane Closures:  Monday through Friday, 8:30 am to 4:00 pm:  As part of private development, construction crews will be milling and overlaying asphalt pavement at the intersection of Sulphur Springs Rd and Irongate Blvd.  Traffic will be shifted onto the continuous center turning lane.  One lane each direction will be kept open.  Appropriate traffic controls will be in place.

AT&T Fiber Work (Sulphur Spring Rd near First Pl)

Expected Lane Closures:  Tuesday through Friday, 8:30 am to 3:30 pm:  AT&T crews will be installing fiber optic lines along the north side of Sulphur Springs Rd near First Pl.  There will be minor traffic interruptions.  Appropriate traffic controls will be in place. 

Annual City Street Paving

Expected Lane Closures:  Monday through Friday, 9:00 AM – 3:00 PM:  City contractor will be performing construction work at the following streets:

  1. Dow St (stream bank restoration work)
  2. Maple St and Burton St (final striping work)
  3. Chaffin Pl (final striping work)
  4. Berkshire Subdivision Roundabout (HC ramps and raised islands concrete & drainage work)
  5. Maple St & Burton St (final striping work)
  6. Saint Andrews Dr at Risen Star Dr (entrance construction work)
  7. Caroline Farms subdivision (casting adjustment work)

Expect lane shifts and traffic interruptions.  Appropriate traffic controls will be in place.

 

TDOT Resurfacing Projects

 

RUTHERFORD SR 99

The grading, drainage, construction of retaining walls, signals and paving on SR-99 (New Salem Hwy) from near I-24 to SR-96 (Old Fort Pkwy)

  • Daily, 9 a.m. – 3 p.m., There will be periodic flagging operations for construction activities.

The resurfacing of SR-99 from Veterans Pkwy to Cason Lane

  • Daily, 8:30 a.m. – 2:30 p.m., There will be flagging operations for resurfacing activities. 

RUTHERFORD COUNTY 266

The grading, drainage, construction of two concrete bulb tee beam bridges, signals, and paving on SR-266 (Jefferson Pike) from SR-102 (LM 5.0) to E. of I-840 (LM 9).

  • Daily, 9 a.m. – 3 p.m., There will be periodic flagging operations for construction activities.        

RUTHERFORD COUNTY, I-24

The resurfacing on I-24 from E of Medical Center Pkwy to Stones River Bridge (MM 76 – 80)

  • Nightly, 8 p.m. – 5 a.m., (Excl. Holiday Restrictions) There will be alternating lane closures EB and WB for installation of pavement markings.

The resurfacing on I-24 from E of Epps Mill Road through Bedford County to the Coffee County Line.

  • Nightly, 8 p.m. – 5 a.m., (Excl. Holiday Restrictions) There will be alternating lane closures EB and WB for paving activities.

The removing & replacing of snowplowable pavement marker lenses on various State Routes

  • Nightly, 8 p.m. – 5 a.m., (Excl. Holiday Restrictions), Alternating NB and SB lane closures for replacing pavement marker lenses.  One lane will remain open at all times

(Source: TDOT)